The prototype fiber cable has been installed on the telescope


We reported that Metrology Camera System had been installed to the Subaru Telescope for the test. MCS, however, is not the only instrument for PFS to have been installed to the telescope. The prototype fiber cable was also routed on the telescope to test the optical performance about a half year ago. The work was done a little long time ago, but we would like to report the installation work of the prototype fiber cable in this article.

In the PFS instrument, the light from the sky is fed to the one end of an optical fiber at the prime focus of the Subaru Telescope and is emitted out to the spectrograph modules from its other end. The spectrograph system is such a long distance away from the prime focus (http://pfs.ipmu.jp/instrumentation.html), that it is crucial to transmit the light in the fiber as efficiently as possible. Previously, we reported the completed integration of 50m-long prototype fiber cable that ranges from the telescope top-end to the clean room to accommodate the spectrograph system. In January 2018, we installed the prototype cable on the Subaru Telescope and tested its optical performance there.

In advance of the installation work, firstly in the Subaru Hilo base facility, we checked a sample of fibers in the fiber cable and confirmed that their optical performances are consistent with those we saw at the factory. We repeated the same check after the cable was transported to the Subaru summit facility, and then went ahead to the installation work.

In the figure, several photos representing the sequence of the work are presented. First of all, the cable was loosely routed on the floor in the telescope area, and then its one end was lifted up by the crane and was installed on the top of the telescope. Then the rest of the cable was routed down along the ladder at the side of the telescope structure, drawn into the telescope enclose building through the clearance near the telescope elevation axis, further routed inside the building and then reached to the inside of the clean room for the spectrograph system.


Snapshots of integration work. The arrows show the sequence of the work: (1) The fiber cable is loosely routed on the floor in the telescope area. (2) & (3) Its one end is lifted by the crane to the telescope top end. (4) the cable is installed on the telescope top-end. (5) The cable is routed down along the ladder at the side of the telescope structure. (6) The other end of the cable is drawn into the telescope enclosure building through the clearance near the telescope elevation axis. (7) The cable is further routed inside the enclosure building. (8) The cable is fully routed up to the clean room for the spectrograph system.

This installation work was carried out on Jan 30, and subsequently for the three days after that, the optical characteristics of the fibers in the cable were measured, with attempts to optimize the way of routing the cable. Through these processes, we managed to obtain not only important know-hows to install the cable but also valuable data about the optical performance of the fibers on the telescope. We will come back in the near future for further data acquisition and cable route optimization to prepare for the real cable installation.


Leave a Reply

Your email address will not be published.